An example. The brand is invented; the method is ours.
THREE WEEKS
THE
ROADMAP
What three weeks leave you with.
A US specialty apparel brand with twelve stores asks how to open thirty more in three years, and its first store in London, without the new ones turning into a cheaper copy of the first. This is what its three weeks with us would leave on the table.
Every benchmark here is published and numbered to its source. Every figure about the brand is invented for this example. A real roadmap uses your numbers.
0 · The brief
What the brand told us before Week 1. The brand is invented for this example; the questions are the ones growing brands ask.
Today
12 stores in 12 US citiesThe plan
30 more in three yearsAbroad
A first store in London, year twoWhere it hurts
Each new store costs more and feels less like the first1 · Week 1: the read
We walked four of the twelve stores, chosen with the brand’s team to cover every format, at a busy time and a quiet one, with the operations lead and each store manager. The other eight we read from plans, photos and sales, so their feel is left blank. Six things, store by store.
Swipe sideways for the whole drawing
What works
- The first table inside the door. In every store it is where customers stop and touch before they look, and the store managers say it sells more than any wall.
- The fitting rooms in the first four stores: daylight or near it, a full-length mirror, a seat, a hook at the right height. Staff call them the place a sale closes.
- Oak, linen and limewash. The palette carries the brand in every format and holds up in photographs and on the phone.
- The street stores under 2,600 square feet. They feel full with half the stock of the centre stores.
- The makers’ wall in the street stores, changed each season. Customers mention it without being asked.
What fails in daily use, and why
- The cash counter: custom walnut, fourteen weeks to make, cracked in three stores where the air is dry. It is also where staff stand with their backs to the floor.
- Fitting rooms: four in every store whatever its size. Queues on weekends in the busy stores; empty rooms in the quiet ones.
- Lighting: three track systems across twelve stores. Lamps can’t move between stores and the white light drifts from warm to cold.
- Deliveries come through the front door in seven of twelve stores, so the floor is restocked while customers shop.
- Walls are built in. Every display change needs a contractor, so the centre stores stopped changing them.
2 · Week 2: keep, change, drop
Sorted with the brand’s team at the table on the Monday of Week 2, then tried in the stores during the week. Nothing is fixed until it has been tried.
Keep
- The first table. Same size and height everywhere; the one piece every store gets first.
- The palette. Oak, linen, limewash, unlacquered brass. Specified once, sourced to the same samples.
- The makers’ wall. One per store, on a system the team can change in an hour.
- The fitting room as a room. Daylight or near it, full-length mirror, a seat, a hook.
Change
- The cash counter. Smaller, freestanding, oak on a steel frame, made in batches; staff face the door.
- Fitting rooms. Number set by the store’s trade, not by habit: three to six.
- Walls. Freestanding bays on one slotted standard, shipped flat, moved by staff.
- Lighting. One track, one lamp family, one colour temperature, ordered centrally.
Drop
- Walnut. It cracks and takes fourteen weeks. Oak does the same job.
- Built-in display walls. They stop the stores changing.
- Front-door deliveries. A lease requirement from now on: a rear or side door, or a delivery window before opening.
3 · Week 2: what we tested
Two ideas were tried in the stores during Week 2, by watching shoppers, and the cost target was checked with makers. Two more were set up in Week 2 to run in the first month after, each with a stop line agreed before anything is built.
| Element | What has to be true | Build | Test | Stop if | |
|---|---|---|---|---|---|
| 01 | The counter | A smaller counter can take a busy Saturday without a queue. | Adapted | Week 2: a plywood mock-up in the Austin store for the weekend; every purchase timed. | the queue at peak is longer than with the old counter. |
| 02 | Fitting rooms by trade | Rooms sized to trade cut the weekend queue without empty rooms on weekdays. | Adapted | Week 2: queues and empty rooms counted in Dallas and Denver over the weekend, set against a year of the brand’s traffic. | the model saves no more than one room in the busy stores. |
| 03 | The cost target | The kit can be built for the target in a street store and a centre store. | Adapted | Week 2: the kit checked with two fixture makers and one contractor from our network. Firm numbers come with drawings. | the makers judge the target out of reach. |
| 04 | Freestanding bays | Staff can change a wall in an hour with one key, and a bay can’t tip. | New | Set up in Week 2: a sample bay ordered. Month one: two staff change it in Chicago, timed. | a change takes longer than ninety minutes or needs a contractor. |
| 05 | One lighting system | One track and lamp family can light all three formats at the same colour. | Off the shelf | Set up in Week 2: lamps ordered. Month one: swapped into two stores and measured with a meter. | the measured colour varies more than the old stores did. |
4 · Week 3: the idea
The idea for the store to build next, in one line: the same five steps from the street to the fitting room, in every store, each a little quieter and more personal than the last. The plan changes with the site; the order does not.
Swipe sideways for the whole drawing
5 · Week 3: the store to build next
The store to build next, as a kit of parts. Heavy pieces are made once and shipped, so every store gets the same thing. The rest is sourced in each market to one specification, so the cost can follow the market without losing the look.
| Part | What it is | Made once and shipped, or sourced in each market | Why |
|---|---|---|---|
| The first table | Solid oak top on a steel base, one size | Made once and shipped | The piece every store has to get right. |
| The counter | Oak on steel, freestanding, staff face the door | Made once and shipped | Replaces the walnut counter; made in batches of six. |
| Wall bays | Freestanding, on one slotted standard; shelves, rails and the makers’ wall all hang from it | Made once, shipped flat | Staff change the store without a contractor. Each bay is restrained against tipping, and anchored for earthquakes in California. |
| Fitting room fronts | Oak frame, linen curtain or door, mirror, seat, hook | Frame made once; mirror and seat sourced | Three to six per store, set by trade. |
| Lighting | One track, one lamp family, one colour temperature | Ordered centrally from one supplier | The same light in every store. Specified to the strictest energy code it has to meet: California’s Title 24, and Part L in the UK. |
| Floor, walls, ceiling | Oak floor or polished concrete; limewash walls | Sourced in each market to the same samples | Cost follows the market; the samples hold the look. |
| Signs | Brass letters, one size family | Made once and shipped | Sized to each landlord’s and city’s rules. |
6 · Week 3: three formats from one kit
One kit, three formats. The plan for each is drawn from the kit before a site is chosen, so real estate knows what each kind of site has to give.
| Format | Size | Where | What changes |
|---|---|---|---|
| Street | 2,000 to 2,600 sq ft | High streets and neighbourhoods | Makers’ wall at the front; three or four fitting rooms. |
| Centre | 2,600 to 3,200 sq ft | Lifestyle and regional centres | Wider first table; five or six fitting rooms; a rear service door written into the lease; the landlord’s design criteria and two-stage drawing review planned in. |
| London | About 2,500 sq ft on two floors | Ground and lower ground, central London | Counter and one fitting room on the ground floor, the rest below; every lit piece fitted for 230 volts. |
7 · Week 3: the cost target
A cost target for the next store, set before anything is drawn and checked with two fixture makers and a contractor in Week 2. Construction and fixtures only, before any landlord allowance. The brand’s figures are invented; the benchmarks are published.
The brand’s last four stores
$245
per square foot · example
The target for the next store
$210
per square foot · example
Across thirty new stores of about 2,600 square feet, $35 per square foot comes to about $2.7 million, in this example. The roadmap sets a separate target for street and centre stores; one is shown here.
For scale: US in-line shop fit-out averaged $157 per square foot in 2026, from $120 in the Midwest to $217 in Northern California and $181 in New York City.1 That benchmark leaves out fixtures, furniture and equipment, which come on top.2 There is no London benchmark directly comparable to the US figure, so a UK cost consultant and two London shopfitters quote the UK version of the kit before the lease is signed.
Where the difference comes from
- Walls. Bays shipped flat and stood up by the contractor, instead of built-in joinery made on site.
- The counter. Oak made in batches of six instead of one walnut counter at a time, on a fourteen-week lead.
- Lighting. One system ordered centrally instead of three, specified store by store.
- Fitting rooms. Three to six, set by trade, instead of four everywhere.
- The rest stays. The palette, the first table and the makers’ wall are where the money still goes.
The target is held store by store through the rollout. If two of the first four new stores come in over it, the kit is redrawn before the fixtures for wave two are ordered.
8 · Week 3: the partners
Who builds it, by role. In a real roadmap these are suggested firms: some the brand already uses, some from our network, each met with the brand before they are chosen.
| Role | In the US | In London | How we brief them |
|---|---|---|---|
| Architect of record | One firm licensed in each state where stores open, working from the store book | A UK practice that knows the landlord’s estate and the borough | The store book, the kit drawings and the cost target, before they draw anything |
| Permit expediter | In cities where permits run long | A planning consultant for signs and any listed building | The opening date and what the lease allows |
| General contractor | Two or three, bid against each other per region | One London shopfitter with retail experience in the centre | A fixed scope from the kit; the fixtures arrive from the maker |
| Fixture maker | One maker for the made‑once pieces, in batches | The same maker, with UK-compliant electrics fitted before shipping | Batch sizes, finishes to the samples, lead time to each opening |
| Lighting supplier | One supplier, ordered centrally | The same family in UK versions | One lamp, one colour temperature, every store |
| Cost consultant | The contractors’ bids checked against the target | A UK quantity surveyor, from the first sketch | The cost target and the kit’s quantities |
| The landlord’s side | Centre landlords’ designated trades for sprinkler and fire alarm tie-ins | The landlord’s surveyor, who approves the drawings | Early, with drawings for each review stage |
9 · Week 3: the order
Which stores come first and what each one needs. The prototype is a refit of a centre store, where the read found the most to fix, so the kit is tested on a trading floor before thirty new stores depend on it. For scale, in 2025 Reformation opened 15 stores9 and Warby Parker 47 net new ones.10
Swipe sideways for the whole drawing
10 · Lease to opening
Planned weeks from possession to opening for one store in each market. Design starts at the letter of intent, so the drawings are ready when the keys are. Published guidance puts a full in-line buildout at 24 to 50 weeks or more.3 New York building applications took 25 days on average from filing to approval in 2026, across all application types;4 Los Angeles quotes 15 to 30 business days for plan check.5 In London, a planning or advertisement consent decision is due in 8 weeks.6 The fixtures are made in parallel, ordered when the lease is signed.
Swipe sideways for the whole drawing
11 · London: what changes
What changes for the first store in London, checked in the extra week a first store abroad gets. Published rules carry the number of their source; the rest is standard UK practice we plan for.
| In the US | In London | What we do about it | |
|---|---|---|---|
| Power | 120 volts | 230 volts11 | Every lit piece fitted with UK electrics at the maker, before it ships. |
| Marking | Fixtures listed by UL or ETL; retail displays to UL 970 since July 202412 | UKCA or CE marking13 | The maker supplies the declaration and the marking for each lit piece. |
| Finishes | Walls and ceilings tested to ASTM E84; hung fabric to NFPA 701 | Euroclass to BS EN 13501‑1: C‑s3,d2 in the shop, B‑s3,d2 in circulation14 | The oak, linen and limewash samples retested; oak linings treated where the class requires it; curtain linen to BS 5867‑2 Type B. |
| Fitting rooms | At least 5% of each cluster accessible, never fewer than one; a 60-inch turning space and a 42-inch bench15 | A self-contained accessible changing cubicle; no set percentage16 | One accessible room in every cluster, on both sides of the Atlantic. |
| Counters | A section no higher than 36 inches15 | A section 1,500 mm wide, no higher than 760 mm, with knee space16 | The oak counter gets one lowered end that meets both. |
| Signs and shopfront | A city sign permit | Advertisement consent, decided in 8 weeks and stricter in conservation areas;7 planning permission for a new shopfront | Both checked for the chosen site before the lease is signed. |
| The landlord | Landlord approval of the drawings | A licence for alterations, inside an agreement for lease that waits on the consents | Lease signed only once the consents are in. |
| On site | Building permit and inspections | Building Regulations approval; principal designer and principal contractor under CDM 2015; an asbestos survey before strip-out; a fire risk assessment | Each one in the London programme from the first week. |
| Shipping | Fixtures by truck | Fixtures by sea, with import duty, VAT and weeks of freight | Ordered earlier, and in the cost target. |
| Handover | Often a “vanilla box”: heating and cooling, walls, floors, basic power and plumbing8 | Usually a shell; “Cat A” and “Cat B” are office terms with no fixed meaning17 | The London build assumes a shell, so services are in the cost from the start. |
12 · The decisions, and when
Each decision has a date, the evidence it rests on, and what would make us stop or change course.
| When | The decision | What it rests on | Stop or change if |
|---|---|---|---|
| Each new site | Sign the lease | The site’s sales forecast and its cost target give a payback inside the brand’s own target. For scale, Reformation reports its stores paying back in under 24 months on average.9 | the payback runs past the brand’s target. |
| End of month nine | Roll out the kit | The prototype’s first three months against the same months last year, with the first month’s novelty discounted | it sells less per square foot than last year, or staff can’t change the walls themselves. |
| Before the London lease | Sign in London | The UK version of the kit quoted; consents checked for the chosen site | the UK build runs more than a quarter over the target, or the consents are refused. |
| Before wave two fixtures are ordered | Order wave two’s fixtures | The four wave-one stores built against the cost target | two of the four come in over the target: the kit is redrawn first. |
| Each new store | Open | The store checked against the prototype before the doors open | anything on the store book’s list is missing. |
13 · After the three weeks
We can stay on beside your team as a monthly retainer, as often as your team wants us: through the next store, the next format or the whole rollout. The roadmap becomes the first months’ plan.
| What carries over | What the rollout does with it | |
|---|---|---|
| The store | The store to build next | The prototype designed and built; the fixture family; the store book every new store follows |
| The build | The cost target, checked with the makers in Week 2 | The kit made in batches; a cost target for every store, held through the build |
| The rollout | The partners and the order | Partners lined up in each market, from the first site visit to opening day |
| Your team | Your people who sat at the table | We work alongside them and leave them with everything we learned |
Sources
Benchmarks only. Nothing about the example brand comes from a source; it is invented.
- 1Cushman & Wakefield, U.S. Retail Fit Out Cost Guide, 2026
- 2ICSC on the 2024 guide’s scope, 2 February 2024
- 3Brookfield Properties, The Store Buildout Blueprint, 2026
- 4NYC Mayor’s Management Report, Department of Buildings, fiscal 2026
- 5LADBS, regular plan check
- 6GOV.UK, Determining a planning application, 2026
- 7DCLG, Outdoor advertisements and signs: a guide for advertisers
- 8American Bar Association, on construction terms in leases
- 9Reformation, Form S‑1, 2026
- 10Warby Parker, fourth quarter and full year 2025 results
- 11Electricity Safety, Quality and Continuity Regulations 2002, regulation 27
- 12Intertek, UL 970 superseding UL 962, July 2024
- 13GOV.UK, Using the UKCA marking, 2026
- 14Approved Document B, volume 2, table 6.1
- 152010 ADA Standards, sections 222, 227, 803, 903 and 904
- 16Approved Document M, volume 2, paragraphs 3.6 and 5.17
- 17Designing Buildings, Fit out of buildings